Hourly Gantt Guide | JustDo

The hourly Gantt in JustDo

2020-09-13

The hourly Gantt shows when work starts and finishes on your JustDo’s calendar. Each row has a bar for a task or a diamond for a milestone. Start with the Gantt, Start Date, Start Time, End Date, End Time and Duration columns in the grid’s column picker.

Set up the schedule

A fresh JustDo uses the hourly engine. An administrator can see which engine is selected in Configure this JustDo → Gantt Settings. If the Gantt extension is missing, enable it under Extensions. A copied JustDo keeps its source’s engine.

Gantt Settings with Hourly Gantt selected and Day-based Gantt (legacy) available

Before the first scheduling edit, open Configure this JustDo → Schedule. Check the weekly shifts and holidays, then choose Lock work schedule. If you start an edit while the weekly hours are unlocked, an administrator can open Schedule settings from the prompt. Repeat the edit after locking. A member can ask a JustDo administrator to do this.

An administrator’s first scheduling edit opens a prompt with a button to open Schedule settings

Read and move work

A working task uses the JustDo’s working hours, breaks, weekends and holidays. With an 8 am–4 pm shift, two working hours from Monday at 3 pm finish Tuesday at 9 am. Choose Elapsed time for work that runs continuously. Those same two hours finish on Monday at 5 pm. Individual owners’ hours and leave are used for resource planning.

Set a task’s dates and times in the grid, or move or resize its bar. Use the Predecessors column or connect the endpoints of two bars to make a dependency. A basket summarizes its children. A milestone marks a zero-duration event, such as clearance to restart.

The green line marks today. Use the Gantt’s zoom and date controls to inspect a short shift or a longer plan. In the column picker, add % Complete to read the progress shown by a bar’s fill. Use the warning icon on a row or the Gantt header to see what needs attention.

Find the work that drives the finish

In Gantt Settings, What counts toward the finish shows the work included. Turn on Slack to add the eight scheduling columns from the picker. Where Workflow Blueprints is installed on an hourly board, it holds Slack on. A critical bar identifies a task with zero or negative Total Slack. The finish-driving chain follows the dependencies that determine when the work can end.

Enter a dependency and count working dates · Read Slack and the critical path · Configure workdays and holidays

For a board using day-based scheduling, see Day-based Gantt (legacy) for baselines, buffers and milestone-based Slack.