Hourly Gantt Dependencies and Working Dates | JustDo

Dependencies in the hourly Gantt

2022-06-08

Enter a dependency on the task that must wait. In its Predecessors cell, type the predecessor’s task number and a link type. You can also drag from the predecessor’s start or finish to the corresponding endpoint of the successor’s bar.

Choose the endpoints

  • Finish-to-start (FS) — B waits to start until A finishes. Enter 123FS, or simply 123.
  • Start-to-start (SS) — B can start once A has started. Enter 123SS.
  • Finish-to-finish (FF) — B can finish once A has finished. Enter 123FF.
  • Start-to-finish (SF) — B can finish once A has started. Enter 123SF.

Count a working-date offset

A plus sign adds a lag. A minus sign adds a lead. In the hourly Gantt each working date counts once, however long its shift. Skip closed dates and holidays. A finish-to-start offset carries the finish time forward to the counted date. If that time is outside the successor’s working hours, an ordinary working task starts at its next opening.

Suppose Friday's only shift is 6–7 pm, Saturday and Sunday are closed, and Monday through Thursday run 8 am–8 pm. Task 123 runs Friday from 6:30 to 6:45 pm. In task B's Predecessors cell, enter 123FS+4D.

After Friday, count Monday (1), Tuesday (2), Wednesday (3) and Thursday (4). Thursday's shift is still open at 6:45 pm, so B's earliest start is Thursday at 6:45 pm. Another dependency can move it later.

Microsoft Project converts a day of lag into working hours using its Hours Per Day setting. The same entry can therefore give a different start time in Project on a calendar with unequal shifts.

Task 123 finishes on Friday at 6:45 pm. Task B’s Predecessors entry is 123FS+4D and its earliest start is the following Thursday at 6:45 pm.

Select a task and open the Dependencies tab in its task pane to see its predecessors and successors. To understand which links control the plan finish, see Hourly Slack and Critical Path.

Follow a link

Open the selected task’s Dependencies tab to see its predecessors and successors. Click a linked task number to inspect that task. The lower pane’s Dependencies tab lists the work you own that is blocking others, and the work blocking your tasks. Administrators can enable the task-chat message for completed predecessors in Gantt Settings.