Day-based Gantt (legacy)
2022-09-04
This reference is for JustDos whose administrator has selected Day-based Gantt (legacy). Existing boards and copies keep their engine. The day-based engine is being phased out. Fresh JustDos use the hourly Gantt.

Baselines
Save a baseline from the task’s Gantt context menu to retain the scheduled dates for later comparison. Use the Baselines tab in the lower pane to select and display a saved baseline. With a baseline selected, the baseline dates and delta columns show how the current plan has moved.
Buffer tasks
To reserve time before a milestone, create a task with the desired duration, add its predecessors, and make it a predecessor of the protected task. Right-click it and choose Set as a buffer task. Its gray bar shrinks as its predecessors use up that allowance. A fully consumed buffer can send a chat notice. In the hourly Gantt a former buffer is scheduled as ordinary work.
Milestone-based Slack and Critical
With Slack enabled in day-based Gantt Settings, follow finish-to-start dependencies into a milestone. Eligible dated tasks on that path show Early Start, Early Finish, Late Start, Late Finish, Free Slack and Total Slack. Margins use working days and the associated milestone is the reference finish. A path with no room to slip is critical. See hourly Slack and Critical Path if your board uses the hourly engine.
Choose the engine
Administrators can open Configure this JustDo → Gantt Settings to change the engine for everyone. The day-based option uses different Slack and Critical calculations. Workflow Blueprints dashboards require the Gantt extension and hourly mode. Choosing hourly again restores dashboard availability.