Slack and Critical Path in the hourly Gantt
2022-09-11
Total Slack is the time by which a task can move before the finish of the work that counts is delayed. Free Slack is how much it can move before it delays a successor, within that total allowance. A critical task has zero or negative Total Slack. A dependency drives the finish when its required start or finish actually sets the next task’s timing along the way to that finish.
Two checks before restart
Start a pressure check and a controls check together at 8 am on a day with an 8 am–5 pm shift. Link both finish-to-start to a zero-duration milestone named Cleared to restart. This milestone is the latest item in the work that counts.
The pressure check takes 8 hours and finishes at 4 pm. The controls check takes 6 hours and finishes at 2 pm. Restart is at 4 pm. The pressure check drives it and has 0h Total Slack. The controls check can use the two hours until 4 pm and has 2h Total Slack.

Now give the controls check 8 hours as well. Both checks finish at 4 pm, both have 0h Total Slack, and both branches drive restart. A delay to either check now delays clearance.

No milestone is required. The hourly engine uses the latest finish of the work that counts. On a board with just the two independent checks, the 8-hour check still sets the finish and the 6-hour check still has two hours of Total Slack.
Read the eight hourly columns
Open Configure this JustDo → Gantt Settings to enable Slack, then add the columns with the grid’s column picker. On an hourly JustDo with Workflow Blueprints installed, Slack is held on. On other hourly JustDos the administrator chooses.
- Early Start and Early Finish
- The earliest start and finish allowed by the task’s placement, duration, calendar and incoming links.
- Late Start and Late Finish
- The latest start and finish allowed by the finish of the work that counts and the task’s downstream requirements and constraints.
- Start Slack and Finish Slack
- The margins at the start and finish respectively. Working tasks count scheduled minutes. Elapsed tasks count clock minutes. A task that has already started can have a fixed start and still have room at its finish.
- Total Slack
- The task’s overall margin. Zero means no remaining margin. A negative figure signals a shortfall, for example against a frozen task.
- Free Slack
- The room before a direct successor’s early timing would move, or before the plan finishes on a terminal task. It is zero when Total Slack is zero or negative.
The first four columns are date-times. The four margins are shown in hours. A dash means there is no figure for that row. Basket rows have no Slack value, and completed tasks have no remaining Slack. A warning can explain a missing or assumed date. A critical flag alone does not establish that every link between two critical tasks drives the finish.
Hourly Gantt guide · Day-based Gantt (legacy)